SAP CO Account Assignment

SAP CO Account Assignment

Normally, when a financial document is entered in SAP FI module , user has the option of entering the cost center in the financial document. However, when documents are entered from different modules or a cross-module financial transaction occurs, such as from MM or SD , there is no option of entering the cost center in the document. In this situation, the SAP system will derive the cost center through automatic SAP CO account assignment, substitutions, or through default settings made in the primary cost element.

Automatic SAP CO Account Assignment

The automatic account assignment has to be configured in the transaction code OKB9 . For posting made in external accounting, such as for price differences, exchange rate differences, etc., the SAP system automatically checks entries in the OKB9 settings and derives the cost center.

If you do not enter a CO object (order, cost center, or project) in external accounting postings made in FI, MM or SD modules and the posting is cost relevant, then the automatic account assignment checks the relevant cost center and makes the posting.

Here are examples of automatic account assignments:

  • Banking fees, exchange rate differences and discounts in FI
  • Minor differences and price differences in MM

The account assignment objects that can be maintained in the transaction OKB9 are:

  • Cost center
  • Profit center (profitability segment)

Normally, the automatic account assignment runs on the company code level along with the CO object. However, if the user wants to make the posting on the business area level, valuation area level or profit center level, it is also available in OKB9 settings. So basically it includes the following levels:

  • Company code level
  • Business area level
  • Valuation area level
  • Profit center level

The above 3 excluding the company code level are used in cases when the account assignment is needed below the company code level.

Prerequisites

Here are the prerequisites of activating automatic SAP CO account assignment:

  • Activation of the cost center accounting
  • Creation of cost centers
  • Maintenance of cost elements

Additionally, you can also create orders and profit centers as per the business requirements.

Settings in Transaction OKB9

Let’s discuss settings that are possible for automatic SAP CO account assignment in OKB9 transaction.

Start SPRO transaction and navigate to the following path:

Controlling – Cost Center Accounting – Actual Postings – Manual Actual Postings – Edit Automatic Account Assignment (OKB9)

Alternatively, you can start OKB9 transaction directly from the command bar.

Transaction OKB9 – SAP CO Account Assignment

  • If you want to have the setting on the company code level only, then enter the company code and the cost element along with the corresponding CO object, i.e. a cost center, an order or a profit center.
  • If you want to have the settings on the valuation area level, then enter the company code and the cost element and chose the ‘valuation area’ option in the account assignment detail as ‘1’.
  • Similarly, if you want to have the settings on the business area or profit center level, then choose the option ‘2’ or ‘3’ respectively.

If you have chosen account assignment detail ‘1’ or ‘2’, then click on ‘Detail per business area/valuation area’ on the left sidebar.

Transaction OKB9 – Details per Business Area / Valuation Area

Default SAP CO Account Assignment

In order to determine the correct CO account assignment, the SAP system performs several checks in the following sequence. First it checks the document which a user is posting. If the cost center is empty in the document, then the system checks if any substitutions are maintained for the particular G/L account . Next, if the substitution is also missing, then the system moves on to the OKB9 settings for automatic SAP CO account assignments. Finally, if these settings are also missing, the SAP system checks master data of the primary cost element (G/L Account) under the tab of Default Account Assignment . You can display this master data using the transaction KA03 .

You can maintain the cost center and the order in the master data of the primary cost element.

SAP Cost Element Master Data

So, basically the order of checks the system makes is:

  • Financial document – Cost center
  • Substitutions – transaction OKC9
  • Automatic account assignments – transaction OKB9
  • Default account assignments – transaction KA03 / KA02

Lastly, if any of the above is not maintained, then the SAP system throws an error ‘Account X requires an assignment to a CO Object’ and doesn’t allow posting of a document.

SAP CO Account Assignment using Substitution

In cases where you don’t need OKB9 or default account assignment, the user can go for user exits where a specific G/L account is mentioned under the company and the value in the cost center is substituted by the cost center given in the substitution.

The transaction for maintaining the substitution is GGB1 .

SAP Create Substitution Transaction

Usage of substitutions for SAP CO account assignment is justified by the business requirement and usually SAP CO account assignment requirements are fulfilled by OKB9 or default account assignments.

Did you like this tutorial? Have any questions or comments? We would love to hear your feedback in the comments section below. It’d be a big help for us, and hopefully it’s something we can address for you in improvement of our free SAP CO tutorials.

Navigation Links

Go to next lesson:  SAP Adjustment Postings

Go to previous lesson:  SAP Profit Center

Go to overview of the course: Free SAP CO Training

4 thoughts on “SAP CO Account Assignment”

it is helpful material i ask for more clear details for using substitution method for Account Assignment. thanks in advance

Sir, I am not receiving the training mails from yesterday 7/1/2019. I have completed my training till here(SAP CO Account Assignment) please do send the rest of the training emails for SAP CO. Hope you will do the needful.

I am getting the same error “Account 500911 requires an assignment to a CO object”. In OKB9, we have given company code, Cost element and ticked the check box ‘Indicator: Find profitability segment using substitution’ (V_TKA3A-BSSUBST) and not filled anything like cost center, order and profit center. in OKC9 we have created substitution. All the process happening through Idoc Message Type SINGLESETTRQS_CREATE and inside BAPI BAPI_SINGLESETTREQS_CREATEMULT triggering and raising this error. Cost center is not maintained in 1. Financial document – Cost center 2. Automatic account assignments – transaction OKB9 and 3. Default account assignments – transaction KA03/KA02 But we have substitution in transaction OKC9 to determine cost centre.

Where woulbe be the issue?

good explanation

Leave a Reply Cancel reply

Do you have a question and want it to be answered ASAP? Post it on our FORUM here --> SAP FORUM !

Your email address will not be published. Required fields are marked *

Save my name, email, and website in this browser for the next time I comment.

sachinhpatil-logo

  • July 30, 2017
  • by Sachin Patil

Normally, when a financial document is entered in SAP FI module, user has the option of entering the cost center in the financial document. However, when documents are entered from different modules or a cross-module financial transaction occurs, such as from MM or SD, there is no option of entering the cost center in the document. In this situation, the SAP system will derive the cost center through automatic SAP CO account assignment, substitutions, or through default settings made in the primary cost element.

Automatic SAP CO Account Assignment

The automatic account assignment has to be configured in the transaction code  OKB9 . For posting made in external accounting, such as for price differences, exchange rate differences, etc., the SAP system automatically checks entries in the  OKB9  settings and derives the cost center.

If you do not enter a CO object (order, cost center, or project) in external accounting postings made in FI, MM or SD modules and the posting is cost relevant, then the automatic account assignment checks the relevant cost center and makes the posting.

Here are examples of automatic account assignments:

  • Banking fees, exchange rate differences and discounts in FI
  • Minor differences and price differences in MM

The account assignment objects that can be maintained in the transaction  OKB9  are:

  • Cost center
  • Profit center (profitability segment)

Normally, the automatic account assignment runs on the company code level along with the CO object. However, if the user wants to make the posting on the business area level, valuation area level or profit center level, it is also available in  OKB9  settings. So basically it includes the following levels:

  • Company code level
  • Business area level
  • Valuation area level
  • Profit center level

The above 3 excluding the company code level are used in cases when the account assignment is needed below the company code level.

Prerequisites

Here are the prerequisites of activating automatic SAP CO account assignment:

  • Activation of the cost center accounting
  • Creation of cost centers
  • Maintenance of cost elements

Additionally, you can also create orders and profit centers as per the business requirements.

Settings in Transaction OKB9

Let’s discuss settings that are possible for automatic SAP CO account assignment in  OKB9  transaction.

Start  SPRO  transaction and navigate to the following path:

Controlling – Cost Center Accounting – Actual Postings – Manual Actual Postings – Edit Automatic Account Assignment (OKB9)

Alternatively, you can start  OKB9  transaction directly from the command bar.

Transaction OKB9 – SAP CO Account Assignment

  • If you want to have the setting on the company code level only, then enter the company code and the cost element along with the corresponding CO object, i.e. a cost center, an order or a profit center.
  • If you want to have the settings on the valuation area level, then enter the company code and the cost element and chose the ‘valuation area’ option in the account assignment detail as ‘1’.
  • Similarly, if you want to have the settings on the business area or profit center level, then choose the option ‘2’ or ‘3’ respectively.

If you have chosen account assignment detail ‘1’ or ‘2’, then click on ‘Detail per business area/valuation area’ on the left sidebar.

Transaction OKB9 – Details per Business Area / Valuation Area

Default SAP CO Account Assignment

In order to determine the correct CO account assignment, the SAP system performs several checks in the following sequence. First it checks the document which a user is posting. If the cost center is empty in the document, then the system checks if any substitutions are maintained for the particular G/L account. Next, if the substitution is also missing, then the system moves on to the  OKB9  settings for automatic SAP CO account assignments. Finally, if these settings are also missing, the SAP system checks master data of the primary cost element (G/L Account) under the tab of  Default Account Assignment . You can display this master data using the transaction  KA03 .

You can maintain the cost center and the order in the master data of the primary cost element.

SAP Cost Element Master Data

So, basically the order of checks the system makes is:

  • Financial document – Cost center
  • Substitutions – transaction  OKC9
  • Automatic account assignments – transaction  OKB9
  • Default account assignments – transaction  KA03 / KA02

Lastly, if any of the above is not maintained, then the SAP system throws an error ‘Account X requires an assignment to a CO Object’ and doesn’t allow posting of a document.

SAP CO Account Assignment using Substitution

In cases where you don’t need  OKB9  or default account assignment, the user can go for user exits where a specific G/L account is mentioned under the company and the value in the cost center is substituted by the cost center given in the substitution.

The transaction for maintaining the substitution is  GGB1 .

SAP Create Substitution Transaction

Usage of substitutions for SAP CO account assignment is justified by the business requirement and usually SAP CO account assignment requirements are fulfilled by  OKB9  or default account assignments.

Post comment

Cancel reply.

You must be logged in to post a comment.

footer logo

I share experience and observations knowledge about the SAP and peripheral systems. 

Copyright © 2022 Sachin H Patil . All Rights Reserved.

Explaining Management Accounting (CO)

After completing this lesson, you will be able to:

  • Explain Management Accounting (CO)

Management Accounting Components

CO contains all of the functions necessary for controlling cost and revenue effectively. It covers all aspects of management controlling and includes many tools for compiling information for company management.

what is co account assignment object

CO consists of several components, as shown in the figure, Components of Management Accounting .

Data that the system creates in other SAP S/4HANA applications can have a direct influence on CO. For example, if you purchase a non-stock item, the system posts an expense to the general ledger (G/L). The system also posts this expense as costs to the cost center for which the item was purchased. This cost center can then pass these costs as overhead to a production cost center.

FI, in the SAP S/4HANA application, is a primary source of data for CO. In fact, most expense postings in the G/L result in a cost posting in CO. These expense postings to the G/L can be journal postings, vendor invoices, or depreciation postings from Asset Management.

Management Accounting provides information that management can use to make decisions. It facilitates the coordination, supervision and optimization of all processes within a company. This involves recording both the consumption of production factors and the services provided by an organization.

In SAP S/4HANA, all relevant cost information from Financial Accounting and Management Accounting is available in real-time on line item level in the central table ACDOCA. Costs and revenues are assigned to different CO account assignment objects such as cost centers, projects, or orders. These Financial Accounting accounts are managed in Management Accounting as cost or revenue elements.

Product Cost Controlling calculates the costs incurred when a service is provided or a product is manufactured. It enables you to calculate the minimum price at which a product can be profitably marketed. The manufacturing area of Logistics also works closely with CO. Bills of material (BOMs) and routings can be used in CO-PC.

Profitability Analysis analyzes the profit or loss of an organization according to individual market segments. In Profitability Analysis, costs are assigned to the revenues of each market segment. This gives you a basis for calculating prices, targeting customers, determining conditions, and choosing sales channels, for example. Sales order management is a primary source for revenue postings from billing documents to revenue postings in CO-PA and PCA. In addition to direct postings from FI, Profitability Analysis (CO-PA) can receive cost assessments from cost centers and ABC processes, settlements of costs from internal orders, and settlements of production variances from cost objects.

Within the Overhead Cost Controlling (CO-OM) area, you can post costs to cost centers, internal orders, and processes from other SAP S/4HANA applications (external costs). Cost centers can then allocate these costs to other cost centers, internal orders, and processes in Activity-Based Costing (ABC). ABC, in turn, can pass costs to cost centers and internal orders. Internal orders can settle costs to cost centers, processes in ABC, and other internal orders.

You use Cost Center Accounting for controlling purposes in your organization. Cost center accounting takes the costs incurred in a company and allocates them to the actual subareas that caused them.

Cost centers are separate areas within a controlling area at which costs are incurred. You can create cost centers according to various criteria including functional considerations, allocation criteria, activities provided, or according to their physical location and/or management area.

An activity type defines the type of activity that can be provided by a cost center. Activity outputs supplied by one cost center (the sending cost center) to other cost centers, orders, or processes, represent the utilization of resources for this sending cost center. You valuate activities using a price calculated on the basis of certain business or management information.

Internal orders are used to plan, collect, and analyze the costs arising from internal activities.

SAP Human Capital Management (HCM) can generate cost postings in CO. SAP HCM allows you to allocate labor costs to various controlling objects. In addition, you can transfer and use planned personnel costs for planning in CO.

Log in to track your progress & complete quizzes

SAP Logo

3047044 - [ECP] The CO account assignment object belongs to company code XXXX, not YYYY - Message No. KI100

  • You are replicating employee master data from SuccessFactors Employee Central to HCM (either On-premise or ECP)
  • In the system log, the following message is displayed:

The CO account assignment object belongs to company code XXXX, not YYYY - Message No. KI100

Environment

  • SAP SuccessFactors Employee Central Integration to SAP Business Suite
  • Employee Central Payroll
  • SAP ERP HCM
  • SAP enhancement package for SAP ERP

KI100 KI 100 CO co account assignment CL_HRSFEC_ITF_ADAPTER IF_HRSFEC_ITF_ADAPTER~ITF_CREATE , KBA , LOD-EC-GCP-PY-EDR , Employee Data Replication , LOD-EC-GCP-PY , Payroll Integration EC to Employee Central Payroll , Problem

About this page

Search for additional results.

Visit SAP Support Portal's SAP Notes and KBA Search .

Privacy | Terms of use | Legal Disclosure | Copyright | Trademark

  • HCM Data Loading Business Objects

Example of Loading a Default Expense Account for a Worker

For every worker who uses Oracle Expenses Cloud, a default expense account must be defined. The Default Expense Account key flexfield is available on the Assignment component of the Worker object.

This topic shows how to load the default expense account for a worker on the worker assignment.

Loading the Default Expense Account on the Assignment

If the expense account is configured with multiple segments, then provide the concatenated value. Separate the segment values using the separator configured for the expense account, as shown in this example.

IMAGES

  1. CO Account Assignment and Attribution with S/4HANA

    what is co account assignment object

  2. SAP solve KI248 Account requires an assignment to a CO object

    what is co account assignment object

  3. SAP FICO

    what is co account assignment object

  4. CO Account Assignment and Attribution with S/4HANA

    what is co account assignment object

  5. Account Assignment Model in SAP: FKMT

    what is co account assignment object

  6. How to Define Chart of Accounts in SAP & Assign Company Code?

    what is co account assignment object

VIDEO

  1. C-Corps CANNOT Use This Method of Accounting

  2. How_To_Create_A_Grey.co_Account_In_NIGERIA

  3. #2A. COST ACCOUNTING- INTRODUCTION

  4. haiiiii everyone!!! Gresiana Herauwani's English assignment "Object Description"

  5. Create Purchase Requisition with Cost Center- Single Account Assignment in #SAP FIORI

  6. Automation of Business Document Processes with MAKIRA by NTT DATA

COMMENTS

  1. CO Account Assignment and Attribution with S/4HANA

    I CO Object as Account Assignment for P&L Postings With S/4HANA cost elements and G/L accounts were merged. Now the general ledger account type determines how the general ledger account can be used in financial accounting (FI-GL) and management accounting (CO). The cost element is determined by the G/L account type "Primary Costs or Revenue" or ...

  2. SAP CO Account Assignment Tutorial

    Enter the valuation area and enter the corresponding CO object, then click save button. Default SAP CO Account Assignment. In order to determine the correct CO account assignment, the SAP system performs several checks in the following sequence. First it checks the document which a user is posting.

  3. CO Account Assignment

    In the CO account assignment key (field COKEY), the respective valid combination of the CO additional account assignments are encrypted. Using this key, you can also activate the account assignment to a profitability segment (CO-PA integration). You maintain the CO account assignment key in the Implementation Guide for Contract Accounts ...

  4. CO Account Assignment

    Cost Object Controlling (CO-PC-OBJ) Product Cost Planning CO-PC-PCP . Actual Costing - Material Ledger CO-PC-ACT . Profit Center Accounting (EC-PCA) Controlling and Profitability Analysis (CO-PA) CO Account Assignment ...

  5. Account Assignment Objects and object types

    Account Assignment Objects and object types. The most important account assignment objects are listed in the following table. The identification code corresponds to the first two characters of the object number (object type). Network Activity Element will have ID code "OK". Sales orders are valid only with make-to-order production (VBAP-KZVBR ...

  6. SAP CO: Account Assignment

    Enter the valuation area and enter the corresponding CO object, then click save button. Default SAP CO Account Assignment. In order to determine the correct CO account assignment, the SAP system performs several checks in the following sequence. First it checks the document which a user is posting.

  7. Explaining Management Accounting (CO)

    Costs and revenues are assigned to different CO account assignment objects such as cost centers, projects, or orders. These Financial Accounting accounts are managed in Management Accounting as cost or revenue elements. Product Cost Controlling calculates the costs incurred when a service is provided or a product is manufactured. It enables you ...

  8. Account Assignment Object in SAP

    Account assignment objects can be objects such as cost centers, internal orders, projects, or business processes. Project System (PS) : The CO object to which postings can be made. In interest calculation, this is a CO object bearing costs and payments. Account assignment objects include WBS elements, network activities, and orders.

  9. 3442629

    KI100: "The CO account assignment object belongs to company code &, not &"; KM183: "No postings can be made to profit center & in company code &". ...

  10. 2335851

    The CO account assignment object belongs to company code A, not B Message No. KI100. Read more... Environment. SuccessFactors BizX, SAP ERP; Employee Central Payroll (ECP, EC Payroll) Product. SAP SuccessFactors HXM Suite, integration for SAP ERP all versions Keywords.

  11. Account Assignment

    The account assignment category determines: The nature of the account assignment (cost center, sales order, and so on) Which accounts are to be charged when the incoming invoice or goods receipt is posted. Which account assignment data you must provide. Account Assignment Categories. Description. Required account assignment data.

  12. Account xxxx Requires an Assignment to a CO Object

    When a document is being posted, system gives a message that A/c xxxx requires an assignment to a CO object. It is basically requiring you to enter a cost center or other CO object (like sales order, production order etc.) this is because a cost element is created for the P&L account. Accounting have created several P&L accounts without cost ...

  13. 3047044

    You are replicating employee master data from SuccessFactors Employee Central to HCM (either On-premise or ECP) In the system log, the following message is displayed: The CO account assignment object belongs to company code XXXX, not YYYY - Message No. KI100

  14. Solved: The CO account assignment object belongs to compan...

    Answers (3) 03-13-2014. Hi to All, Thanks a lot for the help! Yes, the user was trying to approve this invoice that is assigned for the company code 1000 but the line item was assigned for the company code 1100. The finiancial guys are working in change the line item company code to fix this. Thanks! 03-13-2014.

  15. What reference data objects can be shared across business units?

    The following table contains the reference data objects for the Oracle Fusion Applications that can be shared across business units and the method in which the reference data for each is shared. Application Name. Reference Data Object. Method of Sharing. Trading Community Model. Customer Account Relationship.

  16. Account Assignment of Controlling Objects

    This site uses cookies and related technologies, as described in our privacy statement, for purposes that may include site operation, analytics, enhanced user experience, or advertising.You may choose to manage your own preferences.

  17. Example of Loading a Default Expense Account for a Worker

    Separate the segment values using the separator configured for the expense account, as shown in this example. For every worker who uses Oracle Expenses Cloud, a default expense account must be defined. The Default Expense Account key flexfield is available on the Assignment component of the Worker object.

  18. Account Assignment of Controlling Objects

    These rules for the account assignment logic always apply for postings in internal accounting (Controlling). Account assignment distinguishes between true and statistical Controlling objects. True Controlling Objects. Cost centers (for account assignment of costs) Orders (true) Projects (true) Networks. Make-to-order sales orders.

  19. Solved: Account requires an assignment to a CO object

    I assigned the G/L account to a cost centre using OKB9 and was able to post the GR. 01-25-202311:43 AM. Solved: Hi While posting goods receipt, i am getting the following error: Account requires an assignment to a CO object (Message no. KI235). Can anyone pls tell if this.